![]() DOOSAN WINS FRENCH BIOMASS DEAL FROM E.ONA Story by ronisocrates212![]() Doosan wins french biomass deal from e.on![]() Source Doosan Power Systems has been
awarded a major biomass conversion and turbine upgrade project for E.ON's
coal-fired Provence power plant in Gardanne, France. The project will help to create
France's largest biomass-fired power plant to date as part of the E.ON Group's
strategy to deliver "cleaner, higher performance energy". The new unit will generate
electricity from the combustion of wood, including forest chips, green residues
and recovered timber, and will be converted from the existing coal-fired
Provence 4 unit. It will provide 150 MW of power
with base production of more than 7500 hours per year until 2034. Doosan Power Systems will convert
the 20-year-old coal-fired circulating fluidized bed boiler (CFB) and renovate
the steam turbine. The project will be led by German CFB specialist Doosan
Lentjes, which supplied the original CFB technology and key components for the
plant in 1992. At the same time, the company's
turbine specialist, Doosan Skoda Power, will replace the inner steam path of
the existing steam turbine to match the new output and enhance plant
efficiency. Life-time extension works will be undertaken by Doosan Babcock on
the remaining equipment so that the plant is well placed to deliver reliable
performance for a further 20 years. The assembly of the new equipment
will be subcontracted locally to ADF, a French group located in the Fos-Berre
basin that specialises in the maintenance of power generation facilities.
Quartzelec
completes rotor refurb for Ghanaian power plant UK electrical engineering group
Quartzelec has completed a six-month refurbishment and rewinding programme for
a failed generator at Takoradi power station in Ghana. The rotor on the T240-370, 154
MVA generator suffered a double earth fault resulting in severe arcing damage,
so Quartzelec was brought in by independent power producer TAQA. The damaged rotor, which measures
8 metres in length and weighs 36.5 tonnes, was substituted with a new spare
rotor purchased from the OEM to allow the unit to continue operating. Two deep excavations - one of 250
mm and the other of 300 mm axially - were found within two of the forging slots
where material had vapourised at the site of the earth faults. In addition,
more than 10 per cent of the copper winding on the rotor had either been melted
away or become distorted and therefore was unrecoverable. Steve Cooper, business
development manager of power generation at Quartzelec, said: "With a
replacement generator costing in excess of £2 million ($3 million), the client
was looking for a technically competent yet commercially viable solution to
re-establish full generating capacity." The rotor components were
transported to Quartzelec's new, purpose-built facility in Rugby, UK, where
further inspections were carried out. This resulted in a complex weld repair
being carried out on the two damaged slots in order to salvage the forging. A
series of replication tests were then conducted. Arcing damage along the slot
dovetail was also machined off, increasing the dovetail dimensions and a new
set of the retaining rings, snap rings and wider wedges were procured. The rotor was then rewound using
about 80 per cent of the existing copper and a new design of insulation system.
New endwinding packing blocks were also designed, manufactured and fitted.
Siemens
unveils geothermal steam turbine Siemens has unveiled a new steam
turbine for geothermal power plants. The SST-500 GEO serves the power
range up to 120 MW and follows the SST-400 GEO turbine, which was introduced in
2011. The SST-500 GEO is a
single-casing, double-flow condensing turbine. As a derivative of the SST-500
and SST-600 turbine families, it combines the casing and auxiliaries of the
Siemens SST-500 and SST-600 turbines with the geothermal features and steam
path technologies developed, tested and applied by Siemens Energy Services. The SST-500 GEO steam turbine can
be deployed in geothermal plants with a varying range of steam conditions,
being designed for both single and double flash applications. Markus Tacke, chief executive of
the Industrial Power Business Unit of Siemens Energy said the introduction of
the SST-500 GEO "will enable us to participate in the geothermal growth we
currently see in regions such as the eastern coast of Asia, the western coast
of the Americas and parts of Africa". Each SST-500 GEO turbine is designed
uniquely for particular resource conditions by adapting the blade path within
the standardized casing. As with all Siemens geothermal
turbines, the SST-500 GEO is designed with an impulse type steam path, which
due to the robust design has been proven by extensive experience in the
after-market.
Capstone
targets CHP market in Poland Capstone Turbine Corporation is
bringing its low-emissions microturbine energy systems to the Polish market for
the first time and is targeting 10 MW of power by 2015. Capstone will market its
solutions in Poland through Italian company IBT Group, Capstone's exclusive
partner in Italy and Greece. Capstone full range of
microturbines - from 30 kW to 5 MW - will be transformed into certified energy
systems by IBT Group's new Polish sales network. The move is designed to
capitalise on combined heat and power opportunities in Poland. Ilario Vigani, chief executive of
IBT Group, said: "Strategically, Poland has a huge CHP growing potential
as the government is strongly encouraging cogeneration systems in order to
achieve the production of 47.9 GW of electricity by 2030. Having said this, the
country is in the need of reliable technological know-how in this field."
Clark-Reliance
unveils 'sense the sensors' boiler technology Clark-Reliance Corporation has
announced a new remote water level indication system for power and process
boilers. The Eye-Hye SmartLevel system
incorporates new patent-pending technology to intelligently monitor the
condition of its probes which precisely sense the water level in the boiler's
steam drum. When the probes require cleaning
to remove residue and mineral build-up to maintain their accuracy, the system's
smart technology notifies the control room that a probe column blow down is
necessary. Jim Kolbus, Reliance product
manager, said: "This system essentially is able to 'sense the sensors' and
provide precise instructions to operators so they will know when probe cleaning
is needed." "Properly cleaned probes provide the most accurate water
level readings, which allows for optimal quality steam to the turbine,
virtually eliminating water slugs. With the best quality steam, turbines last
longer and an optimized heat rate can be achieved, a foremost goal of any power
producer."
Duke
Energy's IGCC power plant starts commercial operation Duke Energy announced its 618 MW
integrated gasification combined-cycle (IGCC) plant, in the US state of
Indiana, entered commercial operations this month. The plant uses advanced
technology to gasify coal, strip out pollutants and then burn that cleaner gas
to produce electricity. "Coal has powered Indiana
for more than a century," said Duke Energy Indiana's president, Doug
Esamann. "But today's air quality standards require us to use that fuel in
a cleaner, more efficient way. Edwardsport turns coal into a cleaner-burning
fuel and enables us to continue using an abundant local resource." According to the company, this is
the first time the technology has been used on this scale, and the plant is
expected to build up to its long-term level of availability over the next 15
months. "Edwardsport replaces about
500 MW of older coal-fired generation that we recently retired or expect to
retire soon due to new EPA regulations," Esamann said.
According to Duke, the new
Edwardsport IGCC plant will: ·
Produce
ten times as much power as the former plant at Edwardsport, yet with about 70
per cent fewer emissions of sulphur dioxide, nitrogen oxides and particulates
combined: ·
Use
excess steam that would normally be wasted to power a second turbine and
increase plant efficiency and output; ·
Reduce
carbon dioxide emissions per MWh by nearly half compared to the plant it
replaces; ·
Generate
marketable byproducts. The plant will produce sulphur and slag for agricultural
and construction materials. Any revenues from marketable byproducts will go to
customers; and ·
Use
less water than a conventional coal-fired plant. The Edwardsport is one of only
two IGCC plants in the US that are operational, out of more than three dozen
proposed over the last decade. Southern Company's 582 MW Kemper County plant is
the other one. Duke Energy is the largest
electric power holding company in the US, with more than $110 billion in total
assets.
Metso
wins turbine control system rebuild contract Vantaan Energia has chosen Metso
to rebuild the gas turbine control system at its Martinlaakso power plant in
Vantaa, Finland, with the aim to increase turbine reliability and availability. The new automation will replace
the existing turbine control system that has reached the end of its life cycle.
The delivery scope also includes overspeed and vibration protection for the
turbine, changes to turbine hydraulics, field engineering, installation,
factory assembly testing and operator training. A gas turbine simulation model
will test the control application and also be used for training. The turbine
controller will be integrated with the Metso DNA automation system, which now
controls all three Martinlaakso power plant units. The rebuilt control system is
expected to begin operation in November 2013. Once this project is completed,
Metso will have modernised all of Martinlaakso turbines, which representa one
gas turbine and two steam turbines. Vantaan Energia Oy is one of
Finland's largest urban energy companies. It is owned by the cities of Vantaa
(60 per cent) and Helsinki (40 per cent). The Martinlaakso power plant
produces about two-thirds of Vantaa Energia's electricity output and most of
its district heating. The total electrical capacity of the plant is about 195
MW and thermal capacity is 330 MW.
Commercial
floating offshore wind project commences The first commercial offshore
wind measurement campaign using floating LiDAR in European waters has started
in the Irish Sea. FLiDAR NV has deployed one of its
innovative LiDAR buoys for DONG Energy in the southern East Irish Sea. DONG Energy, a leading offshore
wind developer, selected the FLiDAR equipment because of its high accuracy and
cost effective data service. The partnership initially
involves a one year measurement period in the Irish Sea. The technology has been developed
by 3E, global renewable energy consultancy and software services provider,
Offshore & Wind Assistance, the subsidiary of marine contractor Geosea
focusing on operations and maintenance, and Leosphere, the world's leading
LiDAR company. The FLiDAR equipment consists of
a marine buoy equipped with a state-of-the-art buoy-adapted LEOSPHERE
WINDCUBE®v2 LiDAR held in a passive mechanical stabilisation system. It has previously been tested and
validated in the North Sea and in the Irish Sea. The performance has been
analysed and validated by third parties and has been proven to deliver wind
data with accuracy equivalent to standard offshore wind measurements.
Loccioni
highlights coal cash and carbon savings Loccioni'S fossil fuel efficiency
solutions POWdER and CINERIS allow monitoring and regeneration of the coal
combustion process with, the company claims, "significant economic and
environmental impact". POWdER is able to monitor coal
powder fineness in real time, using the innovative and non-intrusive technology
of acoustic emissions. CINERIS is designed to on-line
measure the percentage of unburned carbon in fly ashes. Loccioni gives the example of a
660 MW power plant under ordinary working conditions, which thanks to a
reduction of unburned carbon in fly ashes obtained by the integration of POWdER
and CINERIS, could save 2800 tonnes a year of coal - a €280,000 ($373,000)per
year fuel cost saving and the avoidance of 7000 tonnes of CO2 a year.
James
Walker promises 'fit and forget' reliability James Walker has launched a new
version of its seals for high-volume water pumps such as those used to provide
cooling water in thermal power generation plants. HydroSele CWP is modular in
concept, with each component designed and precision manufactured to fit
together perfectly around the shaft without the requirement for a total
stripdown. The new system can be simply and
quickly retro-fitted to pumps on site and when the integral sealing elements
require replacement - life expectancy is a number of years - this can be easily
achieved in a few hours. Once installed, the units provide
'fit & forget' reliability with no requirement for running maintenance or
adjustment. For the operator not only is the spares stockholding requirement
reduced to a simple set of elastomeric seals for each cartridge but with
reduced maintenance requirements, longer service life and increased
reliability, the overall cost of ownership of both pump and seal unit is
significantly reduced. With thousands of hours logged on
test rigs and units now in operational use on CWP applications at conventional
power stations in the Netherlands, HydroSele CWP shows all the signs of
repeating the success seen by the original design within the hydropower sector.
Schaeffler
steels itself for turbine business Bearings and condition monitoring
specialist Schaeffler has co-developed a new, high-strength quenched and
tempered steel specifically for wind turbine slewing rings that are subjected
to extreme loads during blade and tower adjustment. Schaeffler says this new material
allows full tempering and quenching of the steel and, as a result, provides
outstanding strength properties, even with large ring cross sections. The stell featues zinc thermal
spray surfaces, multi-layer painting and finished seal surfaces which
Schaeffler claims can offer "the highest levels of reliability, bearing
rating life and security against premature damage, such as fatigue of the
raceways and surface corrosion". Due to the material properties
and the applied surface protection, the bearings are suitable for use in
ambient temperatures down to -40oC.
Hempel
offers quick-cure offshore wind turbine coatings International coatings
manufacturer Hempel has launched HEMPADUR 47300, a new coating for offshore
wind towers. Specially formulated for offshore
towers, HEMPADUR 47300 is a low-solvent epoxy mid-coat that Hempel says offers
vastly improved curing times for manufacturers. The coating can be handled just
four hours after application at 20°C, compared to an average of five hours for
standard equivalent coatings. According to Anders Voldsgaard
Clausen, group power generation segment manager at Hempel, the new product
enables manufacturers to reduce production line bottlenecks and increase line
speeds - which could lead to significant cost reductions. "The offshore wind energy
industry is looking to lower costs in every part of the value chain," he
explained. "The curing time of HEMPADUR
47300 means manufacturers can achieve a faster production flow. As a result,
they can coat more towers each shift and use less energy to dry the towers -
which will help drive down the cost of each unit." © 2013 ronisocrates212 |
Stats |